The due dates in the plan end in late 2018, but the "Fix version" is PY7 which ends in August 2018. Should the fix version be changed to PY8 if it isn't going to be finished until PY8?
I added fix version PY8 to show that this activity spans PY7 and PY8.
Thanks.
I added fix version PY8 to show that this activity spans PY7 and PY8.
Thanks.